Canal · Projects

Active projects.

Where the capital-plan dollars are going this year. Five active, one recent close-out.

$9.4M
2026 spend
5
Active
1
Complete
2026 construction calendar

Timeline view.

PROJECT
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
NOV
DEC
In progressSunset Reservoir liner replacement
PlannedWest Point booster station upgrade
In progressSouth Weber air-vac replacement
In progressKaysville 16-inch main replacement
In progressSCADA system upgrade — Phase 2
CompleteLayton lateral lining — 5000 W branch
Project details

What's happening.

In progress

Sunset Reservoir liner replacement

Area: Clinton / West PointBudget: $3.2M

Full HDPE liner replacement at Sunset Reservoir. Brief pressure impacts expected for east-side connections during drain-down.

Planned

West Point booster station upgrade

Area: West PointBudget: $1.8M

Replacement of aging booster pump assemblies. Increases peak-hour pressure capacity by 20%.

In progress

South Weber air-vac replacement

Area: South WeberBudget: $280K

Air-vac assembly replacement on the 12-inch main. One planned pressure window Friday 5:00–8:00 AM.

In progress

Kaysville 16-inch main replacement

Area: South Layton / KaysvilleBudget: $2.4M

8-block section of 1962 CI main replaced with ductile iron. Open-cut construction on 200 N.

In progress

SCADA system upgrade — Phase 2

Area: System-wideBudget: $1.7M

Replacement of legacy SCADA controllers at 14 sites. No pressure impacts.

Complete

Layton lateral lining — 5000 W branch

Area: West LaytonBudget: $620K

CIPP lining of 2,400 linear feet of 1948 concrete lateral. Closed out Mar 28.